Delivered

Topic Software update Description Notes
TKR Digi TkrDigi v2r6 includes charge sharing and ion signal two available routines, not enough to recover TKR hit deficit in MC
ACD Digi GR-v11 better single photo-electron signal simulation by extending Poisson fluctuations to first dynodes amplification  
CAL Calibration Procedure column-wise charge injection in CAL CPT online scripts correct non-linearities in charge injection improved CAL calibration but did not solve energy shift; will be default calibration mode for the LAT, not relevant for simulation
CalRecon GR-v11 correct logs and inter-range cross-talk require mapping of cross-talk for the LAT
Hadronic physics list GR-v12   improved model for hadronic interactions (Bertini model up tp 10GeV, QGSP model up to 20GeV)
TKR material audit GR-v12 real TKR thin converter thickness 8% lower wrt to original design

List of planned deliverables and expected delivery

Topic Expected delivery Description Notes
TKR material audit end september update mass of passive material to real values from measurements known missing mass in current model mostly around active area
CAL material audit end september check and update CAL mass and materials preliminary surveys indicate good model
TKR alignment in MC quick fix available in GR-v12 fix bug in MC alignment checking out alternative alignment strategy
New mass simulation end september with latest sim-recon package will be used to re-evaluate TKR hits deficit and CAL energy shift in simulation
Special TKR geometry simulation in progress vacuum layer between silicon layers and tray core performed to check penetration of delta rays in a more realistic geometry; preliminary results indicate little effect on TKR hits
Low-energy simulations in progress systematic test of LE EM physics list in G4 and range cutoff studies preliminary results indicate no effect of range cutoffs and a non-perfect control of LE physics list in our simulation
background simulations with higher TKR hits end september increase artificially number of TKR hits to mimick BT data will use alignment bug and will check effect on background rejection
background simulation with shifted CAL energies end september artificially scale simulated CAL energies and most important CAL variables to mimick BT data will check effect on background rejection and reconstruction algorithms
final best physics list november final MC tuning should flow into the Service Challenge 1 year run. it will includes best physics list and modification to geometry

Currently planned MC checks:

  • restate data/MC agreement with v7 MC for CAL
  • cross-check TKR PSF and HIT summary posted in the agenda on october 17
    • check effect of the extra neutral vertex on the PSF - any bias introduced?
    • double check beam spot from David P for all simulated runs
    • check cerenkov pressure for run at 200GeV - Johan found it was wrong?
  • verify alignment effect in v7
    • seems negligible from Johan MC-MC comparison (links on BeamTest:Good Runs), while cerenkov pressure seem to have been wrong in earlier MC
    • sistematically check cerenkov pressure systematics with a scan
  • verify effect of cuts on hit deficit
    • run 1 sim with extended beam spot and cut on differnt parts to check possible effects
    • apply nicola's cuts on beam spot plot and check if special spots are selected
    • add fiducial cuts in the selection?
  • smearing routine to align CAL MC variables to data values
  • scan extra material along beam line after above realignment

Powered by Atlassian Confluence, the Enterprise Wiki. (Version: 2.5.8 Build:#814 Oct 02, 2007) - Bug/feature request - Contact Administrators